Brighton and Hove City Council's Cabinet has approved moving traffic cameras at five junctions in the city, following a six-week public consultation. The decision was taken on Thursday 12 November 2026 and is subject to call-in until 20 November. If it is not called in, it comes into force on 21 November.
The five camera locations
Cabinet approved moving traffic enforcement at the first five locations, where the council says restrictions are regularly ignored:
- Carden Avenue onto Carden Crescent: one-way street restriction
- London Road onto New England Road: prohibited left turn
- Ditchling Road onto Baker Street: prohibited left turn
- West Street onto Rottingdean High Street: prohibited right turn
- Francis Street: motor vehicle prohibition, except for access
What the consultation found
Across all five sites the council received 704 responses: 403 in favour, 253 against and 48 neutral. Support varied by location:
- Rottingdean High Street and West Street: 71.8% in favour, 23.8% against (206 responses)
- Carden Crescent and Carden Avenue: 54.8% in favour, 39.5% against (124 responses)
- Francis Street and Ditchling Road: 52.6% in favour, 39.1% against (133 responses)
- Ditchling Road and Baker Street: 50% in favour, 42% against (112 responses)
- London Road and New England Road: 47.3% in favour, 43.4% against (129 responses)
London Road and New England Road was the only location where support was below half of respondents. The earlier consultation report from August explains how residents were asked for their views.
Cost and funding
The council's report puts camera installation at the five sites at £94,000, to be funded from the CCTV capital programme, which is paid for by borrowing.
How the cameras will be used, with warnings first
Cabinet also approved a citywide policy on how the powers are used. The council says enforcement will only be introduced where there is clear evidence of safety concerns, congestion or repeated non-compliance. The policy includes public consultation, awareness raising and warning periods before penalties are issued.
New locations will be chosen using that evidence, then consulted on and reviewed. Cabinet delegated authority to the Corporate Director for City Operations to approve future locations, in consultation with the lead member for transport.
What the council told ImJustBrighton
In answers to ImJustBrighton's questions on 18 November 2026, the council said:
- Start date: enforcement at the five locations is expected to begin from February 2027.
- Human check: council officers will review each contravention before a warning notice or penalty charge notice is sent.
- Warning period: for the first six months, the registered keeper gets a warning notice for a first contravention at a camera location. A second contravention by the same vehicle during that period may bring a penalty charge notice.
- Cost: installing cameras at all five sites is estimated at about £94,000.
- Fine income: any surplus income from penalty charge notices can only be spent on purposes set out in law, including traffic management, public transport such as free bus passes for older and disabled passholders, highways maintenance, air quality and environmental improvements.
How ImJustBrighton reported this
ImJustBrighton put written questions to Brighton and Hove City Council's press office on 14 November 2026. The answers above, and Cllr Trevor Muten's statement, were sent to us on 18 November 2026.
Councillor Trevor Muten, Cabinet Member for Transport and City Infrastructure:
"Evidence led enforcement will help make our roads safer and ensure existing traffic restrictions are respected.
"They're in place for a very good reason, whether that's protecting people walking, crossing the road and cycling, improving road safety, reducing congestion or keeping traffic moving.
"We've already seen significant improvements in compliance at our School Streets sites and we're now developing a clear, transparent framework for how these powers should be used in future.
"This isn't about widespread enforcement. It's about taking a targeted approach, focusing on locations where there is evidence of ongoing problems and where action can deliver real benefits for residents, businesses and everyone travelling around the city."
Roadworks charge
The same Cabinet report also covered the council's planned lane rental scheme for roadworks. Our separate explainer sets out how the proposed £2,500 a day charge would work.
Sources
Cabinet decision: Managing the Transport Network, 12 November 2026. Full Cabinet report. Press enquiries: news@brighton-hove.gov.uk.